The correct answer is B: Risk avoidance. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You work as the project manager for BlueWell Inc. You are monitoring the project performance. You want to make a decision to change the project plan to eliminate a risk in order to protect the project objectives. Which of the following strategies will you use to tackle the risk?

Options

  • ARisk mitigation
  • BRisk avoidance
  • CRisk acceptance
  • DRisk transference

Topics

#Risk avoidance#Threat response#Risk response strategies#Project monitoring