nerdexam
PMIPMI

PMI-RMP · Question #38

PMI-RMP Question #38: Real Exam Question with Answer & Explanation

The correct answer is D: Acceptance. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

Lisa is the project manager of the FKN project for her organization. She is working with Sam, the CIO, to discuss a discount the vendor has offered the project based on the amount of materials that is ordered. Lisa and Sam review the offer and agree that while their project may qualify for the discounted materials the savings is nominal and they would not necessarily pursue the savings. Lisa documents this positive risk response in the risk register. What risk response is this?

Options

  • AEnhance
  • BTransference
  • CShare
  • DAcceptance

Topics

#Positive Risk Response#Opportunity Management#Risk Acceptance (Opportunity)#Risk Register

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions