PMI-RMP · Question #520
PMI-RMP Question #520: Real Exam Question with Answer & Explanation
The correct answer is C: Review published operational experience reports.. Reviewing published operational experience reports from similar projects or industries can help the risk manager objectively identify risks for the chemical laboratory project. These reports provide valuable insights into potential risks and lessons learned from other projects. O
Question
A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks. What should the risk manager do?
Options
- AImport a risk register from other industry chemical laboratories.
- BDefine chemical laboratory safety risk thresholds.
- CReview published operational experience reports.
- DDraft threat and opportunity risks that come to mind.
Explanation
Reviewing published operational experience reports from similar projects or industries can help the risk manager objectively identify risks for the chemical laboratory project. These reports provide valuable insights into potential risks and lessons learned from other projects. One of the tools and techniques for the identify risks process is data gathering. Data gathering is the process of collecting information from various sources to identify potential risks that may affect the project objectives. One of the data gathering techniques is document analysis, which involves reviewing and analyzing available project documents and other information sources to identify potential risks. Some of the documents that can be analyzed are project charter, project management plan, stakeholder register, assumptions log, agreements, and lessons learned. One of the information sources that can be useful for identifying risks in a project constructing a chemical laboratory is published operational experience reports. These are reports that document the experiences, lessons learned, best practices, and recommendations from other organizations or projects that have constructed or operated chemical laboratories. These reports can provide valuable insights into the common risks, challenges, and opportunities that are associated with chemical laboratory projects, such as safety hazards, environmental regulations, equipment failures, design specifications, quality standards, and stakeholder expectations. By reviewing published operational experience reports, the risk manager can objectively identify risks that are relevant and applicable to their project, as well as learn from the successes and failures of others.