PMI-RMP · Question #585
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to…
The correct answer is A. Perform an assumptions and constraints analysis. When conflicts arise among diverse stakeholders, many conflicts stem from differing assumptions about the project and constraints imposed on it. Performing an assumptions and constraints analysis as the first step helps surface hidden or conflicting assumptions that are driving…
Question
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen. What should the risk manager do first?
Options
- APerform an assumptions and constraints analysis.
- BUse the Wideband Delphi method.
- CUse the brainstorming technique.
- DPerform a strength, weaknesses, opportunities, and threats (SWOT) analysis.
How the community answered
(55 responses)- A82% (45)
- B11% (6)
- C2% (1)
- D5% (3)
Explanation
When conflicts arise among diverse stakeholders, many conflicts stem from differing assumptions about the project and constraints imposed on it. Performing an assumptions and constraints analysis as the first step helps surface hidden or conflicting assumptions that are driving disagreement and risk. Brainstorming and Wideband Delphi are group techniques best used after the environment is better understood. A SWOT analysis is useful but broader; assumptions and constraints analysis is more targeted at the root cause of stakeholder conflict and is the foundational first step in risk identification within a conflicted environment.