nerdexam
PMIPMI

PMI-RMP · Question #56

PMI-RMP Question #56: Real Exam Question with Answer & Explanation

The correct answer is A: Activity duration estimates. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?

Options

  • AActivity duration estimates
  • BSchedule management plan
  • CRisk management plan
  • DActivity cost estimates

Topics

#Identify Risks#Activity Duration Estimates#Schedule Risk#Risk Identification Inputs

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions