nerdexam
PMIPMI

PMI-RMP · Question #55

PMI-RMP Question #55: Real Exam Question with Answer & Explanation

The correct answer is C: Risk register and the risk management plan. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. When the project manager begins the plan risk response process, what two inputs will she need?

Options

  • ARisk register and the risk response plan
  • BRisk register and power to assign risk responses
  • CRisk register and the risk management plan
  • DRisk register and the results of risk analysis

Topics

#Risk response planning#Process inputs#Risk register#Risk management plan

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions