PMI-RMP · Question #54
PMI-RMP Question #54: Real Exam Question with Answer & Explanation
The correct answer is C: List of identified risks. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.
Options
- AList of mitigation techniques
- BList of key stakeholders
- CList of identified risks
- DList of potential responses
Topics
#Risk register content#Identify Risks process#Risk responses#Project documents