PMI
PMI-RMP · Question #566
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #566. The question stem and answer options stay visible for context.
Risk Process Facilitation
Question
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected. What should the risk manager do first?
Options
- ARemove the activity padding.
- BReview the risk response plan.
- CUpdate the risk contingency plan.
- DUpdate the schedule constraints.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Schedule contingency#Risk response review#Stakeholder concerns#Risk process management