nerdexam
PMI

PMI-RMP · Question #565

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to…

The correct answer is C. Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime. When a risk response creates a new (residual) risk, the risk manager must ensure the appropriate authority - in this case the project sponsor - is aware of and accepts the residual risk before the response is executed. The sponsor holds organizational authority over the…

Risk Strategy and Planning

Question

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost. What should the risk manager do?

Options

  • ADocument the concern over the potential excessive additional cost.
  • BManage the potential excessive additional cost as a new risk.
  • CEnsure the project sponsor has the risk appetite for the residual risk created by allowing overtime.
  • DPrepare a detailed response plan for the residual risk with a clear owner and time line to ensure

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    4% (2)
  • C
    83% (39)
  • D
    2% (1)

Explanation

When a risk response creates a new (residual) risk, the risk manager must ensure the appropriate authority - in this case the project sponsor - is aware of and accepts the residual risk before the response is executed. The sponsor holds organizational authority over the project's risk appetite and budget; only they can sanction accepting the cost exposure that overtime may create. Simply documenting the concern (A) or preparing a detailed residual risk response plan (D) without sponsor buy-in skips the critical approval step. Treating the cost overrun as a separate new risk (B) is premature until the sponsor's acceptance of the residual risk is confirmed.

Topics

#Risk response planning#Secondary risk#Risk appetite#Stakeholder engagement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice