nerdexam
PMI

PMI-RMP · Question #565

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work

The correct answer is C. Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.. When a risk response creates a new (residual) risk, the risk manager must ensure the appropriate authority - in this case the project sponsor - is aware of and accepts the residual risk before the response is executed. The sponsor holds organizational authority over the project's

Risk Strategy and Planning

Question

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost. What should the risk manager do?

Options

  • ADocument the concern over the potential excessive additional cost.
  • BManage the potential excessive additional cost as a new risk.
  • CEnsure the project sponsor has the risk appetite for the residual risk created by allowing overtime.
  • DPrepare a detailed response plan for the residual risk with a clear owner and time line to ensure

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    4% (2)
  • C
    83% (39)
  • D
    2% (1)

Explanation

When a risk response creates a new (residual) risk, the risk manager must ensure the appropriate authority - in this case the project sponsor - is aware of and accepts the residual risk before the response is executed. The sponsor holds organizational authority over the project's risk appetite and budget; only they can sanction accepting the cost exposure that overtime may create. Simply documenting the concern (A) or preparing a detailed residual risk response plan (D) without sponsor buy-in skips the critical approval step. Treating the cost overrun as a separate new risk (B) is premature until the sponsor's acceptance of the residual risk is confirmed.

Topics

#Risk response planning#Secondary risk#Risk appetite#Stakeholder engagement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice