PMI-RMP · Question #17
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are…
The correct answer is C. Transference. Transference is the negative risk response strategy that shifts the ownership and financial responsibility of a risk to a third party, such as an insurer or contractor.
Question
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?
Options
- AAvoidance
- BSharing
- CTransference
- DMitigation
How the community answered
(17 responses)- A6% (1)
- C88% (15)
- D6% (1)
Why each option
Transference is the negative risk response strategy that shifts the ownership and financial responsibility of a risk to a third party, such as an insurer or contractor.
Avoidance changes the program plan to eliminate the risk entirely, rather than handing ownership of it to a third party.
Sharing is a positive risk response used to allocate ownership of an opportunity to a third party that is better positioned to capture the benefit, not to transfer a negative risk.
Transference involves contracting with an outside party - such as hiring a vendor, purchasing insurance, or using fixed-price contracts - so that the third party assumes responsibility for managing and bearing the consequences of the risk event. It does not eliminate the risk, but it moves the financial and operational burden away from the program team. This is the appropriate strategy when management wants a third party to own the risk.
Mitigation reduces the probability or impact of a risk event but retains ownership of the risk within the program team.
Concept tested: Transference as negative risk response to third party
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok