PMI-RMP · Question #18

PMI-RMP Question #18: Real Exam Question with Answer & Explanation

The correct answer is C: Acceptance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?

Options

  • AEnhance
  • BExploit
  • CAcceptance
  • DShare

Topics

#Risk response strategies#Negative risks#Threats#Risk planning