PMIPMI
PMI-RMP · Question #18
PMI-RMP Question #18: Real Exam Question with Answer & Explanation
The correct answer is C: Acceptance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?
Options
- AEnhance
- BExploit
- CAcceptance
- DShare
Topics
#Risk response strategies#Negative risks#Threats#Risk planning
Community Discussion
No community discussion yet for this question.