nerdexam
PMI

PMI-RMP · Question #19

Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on…

The correct answer is D. Avoidance. Removing the requirements that caused the risk exposure is a textbook example of the Avoidance response, which eliminates the threat by changing the project plan.

Risk Strategy and Planning

Question

Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?

Options

  • AMitigation
  • BTransference
  • CAcceptance
  • DAvoidance

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    15% (5)
  • D
    76% (26)

Why each option

Removing the requirements that caused the risk exposure is a textbook example of the Avoidance response, which eliminates the threat by changing the project plan.

AMitigation

Mitigation reduces the probability or impact of the risk but does not eliminate it; removing the requirements entirely goes beyond mitigation.

BTransference

Transference shifts ownership of the risk to a third party, but no third party is involved here - the risk is eliminated by changing scope.

CAcceptance

Acceptance acknowledges the risk and takes no preemptive action, whereas deliberately removing requirements to prevent the risk is an active elimination strategy.

DAvoidanceCorrect

Avoidance is the negative risk response that eliminates the threat entirely by changing the project scope, schedule, or plan so the risk can no longer occur. By removing the requirements tied to the high-probability, high-impact risk event, the team has eliminated the conditions that would allow the risk to materialize. Although this changes project scope, it successfully releases the project from that risk exposure.

Concept tested: Risk avoidance by eliminating risk-causing requirements

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Response Strategies#Threat Responses#Risk Avoidance

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice