nerdexam
PMIPMI

PMI-RMP · Question #20

PMI-RMP Question #20: Real Exam Question with Answer & Explanation

The correct answer is A: Corrective action. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

Options

  • ACorrective action
  • BRisk audit
  • CTechnical performance measurement
  • DEarned value management

Topics

#Risk response#Corrective action#Risk control#Project monitoring and controlling

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions