nerdexam
PMIPMI

PMI-RMP · Question #21

PMI-RMP Question #21: Real Exam Question with Answer & Explanation

The correct answer is D: SV=EV-PV. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

Options

  • ASV=EV/PV
  • BSV=PV-EV
  • CSV=EV/AC
  • DSV=EV-PV

Topics

#Schedule Variance#Earned Value Management#Project Performance Measurement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions