PMIPMI
PMI-RMP · Question #21
PMI-RMP Question #21: Real Exam Question with Answer & Explanation
The correct answer is D: SV=EV-PV. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?
Options
- ASV=EV/PV
- BSV=PV-EV
- CSV=EV/AC
- DSV=EV-PV
Topics
#Schedule Variance#Earned Value Management#Project Performance Measurement
Community Discussion
No community discussion yet for this question.