PMI-RMP · Question #586
A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present
The correct answer is B. Conduct a risk assessment process for the critical stage.. When client experts express concern about specific activities at a critical stage, the risk manager's first responsibility is to understand and assess the risk associated with that concern before taking any action. Conducting a risk assessment for the critical stage identifies wh
Question
A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative. What should the risk manager do first?
Options
- AReview and update the project quality management plan.
- BConduct a risk assessment process for the critical stage.
- CCreate a more detailed work breakdown structure (WBS).
- DAdd additional time to the delivery plan to cover issues.
How the community answered
(38 responses)- A5% (2)
- B76% (29)
- C5% (2)
- D13% (5)
Explanation
When client experts express concern about specific activities at a critical stage, the risk manager's first responsibility is to understand and assess the risk associated with that concern before taking any action. Conducting a risk assessment for the critical stage identifies what risks exist, their probability, and their potential impact-providing the evidence needed to decide whether to change the plan, add time, or adjust the WBS. Updating the quality plan, revising the WBS, or adding time are potential responses, but they should only follow a risk assessment that justifies those actions.