PMI-RMP Question #586: Real Exam Question with Answer & Explanation

The correct answer is B: Conduct a risk assessment process for the critical stage.. If client's experts express discomfort with some activities at a critical stage, the first step for the risk manager is to conduct a risk assessment process for that stage. This assessment will help identify the specific risks associated with the activities in question, evaluate

Perform Targeted Risk Analysis

Question

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative. What should the risk manager do first?

Options

  • AReview and update the project quality management plan.
  • BConduct a risk assessment process for the critical stage.
  • CCreate a more detailed work breakdown structure (WBS).
  • DAdd additional time to the delivery plan to cover issues.

Explanation

If client's experts express discomfort with some activities at a critical stage, the first step for the risk manager is to conduct a risk assessment process for that stage. This assessment will help identify the specific risks associated with the activities in question, evaluate their potential impact, and develop appropriate mitigation strategies. This ensures that the project plan is robust and that all stakeholders are confident in its execution.

Topics