PMI-RMP · Question #587
The stakeholders of a building construction project are not comfortable with the project manager's handling of the project as they believe there is a financial risk. The project manager asks the risk
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #587. The question stem and answer options stay visible for context.
Question
The stakeholders of a building construction project are not comfortable with the project manager's handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold. What should the risk manager do first to demonstrate this to the stakeholders?
Options
- AGather other project risk historical information.
- BGather and reconcile project risk report data.
- CWork with the sponsor to convince the risks are under control.
- DWork with the team to ensure the project is in good health.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.