PMI-RMP · Question #519
PMI-RMP Question #519: Real Exam Question with Answer & Explanation
The correct answer is A: Quantitative risk analysis. Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. The team should perform quantitative risk analysis, which is the
Question
The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk. What should the team perform in this scenario?
Options
- AQuantitative risk analysis
- BRisk response planning
- CMonitor and control risks
- DRisk urgency assessment
Explanation
Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making.
Topics
Community Discussion
No community discussion yet for this question.