nerdexam
PMIPMI

PMI-RMP · Question #519

PMI-RMP Question #519: Real Exam Question with Answer & Explanation

The correct answer is A: Quantitative risk analysis. Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. The team should perform quantitative risk analysis, which is the

Perform Targeted Risk Analysis

Question

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk. What should the team perform in this scenario?

Options

  • AQuantitative risk analysis
  • BRisk response planning
  • CMonitor and control risks
  • DRisk urgency assessment

Explanation

Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making.

Topics

#Quantitative risk analysis#Risk exposure#Risk thresholds#Risk escalation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions