PMI-RMP · Question #521
PMI-RMP Question #521: Real Exam Question with Answer & Explanation
The correct answer is B: Conduct a risk reassessment and reserve analysis.. The project manager should reassess the risks and analyze the reserve to determine if any adjustments can be made to accommodate the expected additional work. This will help in identifying potential budget-saving measures and making informed decisions on how to proceed. Risk reas
Question
Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget. What should the project manager do next?
Options
- ARequest a budget relief using the management reserve.
- BConduct a risk reassessment and reserve analysis.
- CReview the consequences of potential changes.
- DCoach stakeholders on risk identification practices.
Explanation
The project manager should reassess the risks and analyze the reserve to determine if any adjustments can be made to accommodate the expected additional work. This will help in identifying potential budget-saving measures and making informed decisions on how to proceed. Risk reassessment is the process of reanalyzing existing project risks and identifying new risks throughout the project life cycle. Reserve analysis is the process of estimating the amount of contingency reserve and management reserve needed to account for the uncertainty and variability of the project. In this case, the project manager should conduct a risk reassessment and reserve analysis as the next step, because the budget overruns during execution have changed the risk profile of the project and reduced the available funds to handle future risks. By conducting a risk reassessment, the project manager can update the risk register and the risk response plan with the current status of the project risks and the effectiveness of the risk responses. By conducting a reserve analysis, the project manager can determine if the remaining contingency reserve and management reserve are sufficient to cover the potential impact of the project risks, and request additional funds if needed.
Topics
Community Discussion
No community discussion yet for this question.