nerdexam
PMIPMI

PMI-RMP · Question #631

PMI-RMP Question #631: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #631. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed. Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options

  • ASchedule and resource assumptions
  • BContingency reserves
  • CWork breakdown structure (WBS)
  • DRisk impact matrix

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Performance analysis#Risk mitigation#Planning assumptions#Root cause analysis
Full PMI-RMP PracticeBrowse All PMI-RMP Questions