PMIPMI
PMI-RMP · Question #60
PMI-RMP Question #60: Real Exam Question with Answer & Explanation
The correct answer is A: Acceptance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
There are seven risks responses that a project manager can choose from. Which risk response is appropriate for both positive and negative risk events?
Options
- AAcceptance
- BSharing
- CTransference
- DMitigation
Topics
#Risk responses#Threats and opportunities#Risk management fundamentals#Acceptance risk response
Community Discussion
No community discussion yet for this question.