PMI-RMP · Question #60

PMI-RMP Question #60: Real Exam Question with Answer & Explanation

The correct answer is A: Acceptance. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

There are seven risks responses that a project manager can choose from. Which risk response is appropriate for both positive and negative risk events?

Options

  • AAcceptance
  • BSharing
  • CTransference
  • DMitigation

Topics

#Risk responses#Threats and opportunities#Risk management fundamentals#Acceptance risk response