PMIPMI
PMI-RMP · Question #300
PMI-RMP Question #300: Real Exam Question with Answer & Explanation
The correct answer is A: Probability of achieving time and cost estimates. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?
Options
- AProbability of achieving time and cost estimates
- BWatch list of low-priority risks
- CPriority list of risks
- DRisks grouped by categories
Topics
#Qualitative Risk Analysis#Risk Register Updates#Risk Management Outputs#PMI-RMP Processes
Community Discussion
No community discussion yet for this question.