nerdexam
PMIPMI

PMI-RMP · Question #79

PMI-RMP Question #79: Real Exam Question with Answer & Explanation

The correct answer is C: Quantitative risk analysis process will be completed again after the risk response planning and as a part. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?

Options

  • AQuantitative risk analysis process will be completed again after the cost management planning and as a
  • BQuantitative risk analysis process will be completed again after new risks are identified and as part of
  • CQuantitative risk analysis process will be completed again after the risk response planning and as a part
  • DQuantitative risk analysis process will be completed again after the plan risk response planning and as

Topics

#Quantitative Risk Analysis#Risk Monitoring and Control#Risk Management Process#Iterative Processes

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions