PMI-RMP · Question #78

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that…

The correct answer is C. Integrated change control. Integrated Change Control is the process responsible for reviewing all change requests and formally communicating the approval or denial decision to stakeholders. It serves as the central mechanism for managing changes across all knowledge areas. The configuration management…

Risk Monitoring and Reporting

Question

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?

Options

  • AConfiguration management system
  • BScope change control system
  • CIntegrated change control
  • DChange log

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    86% (18)

Explanation

Integrated Change Control is the process responsible for reviewing all change requests and formally communicating the approval or denial decision to stakeholders. It serves as the central mechanism for managing changes across all knowledge areas. The configuration management system (A) manages the technical specifications of deliverables. The scope change control system (B) specifically handles scope changes but reports through integrated change control. The change log (D) is a document that records change requests and their status, but it is an output-not the process that communicates decisions. Integrated change control is the authoritative process for change decisions.

Topics

#Integrated Change Control#Change Request#Change Control Board (CCB)#Communication of Change Decisions