PMI-RMP · Question #77

Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in thi

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #77. The question stem and answer options stay visible for context.

Stakeholder Engagement

Question

Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project. She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

Options

  • A156
  • B3,003
  • C78
  • D6,084

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Communication Channels Calculation#Stakeholder Communication#Communication Management