PMIPMI
PMI-RMP · Question #76
PMI-RMP Question #76: Real Exam Question with Answer & Explanation
The correct answer is B: Beth, because she has the authority to respond to the risk event. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Bill is the project manager for a project that will last six months and has a budget of $580,000. In this project a high-risk has been identified with the new materials the project will be using. Bill would like to assign one person, Beth, to be responsible to monitor this risk. Bill assigns Beth the authority to respond to the risk event if it appears in the risk events that is likely to happen. In addition, Bill hires a consultant to work with Beth on this area of the project. In this instance, who is the risk response owner?
Options
- ABill, because he is the project manager
- BBeth, because she has the authority to respond to the risk event
- CBeth and the consultant are the risk owners
- DThe consultant working with Beth, because this is transference
Topics
#Risk response owner#Risk roles and responsibilities#Risk monitoring#Accountability
Community Discussion
No community discussion yet for this question.