PMIPMI
PMI-RMP · Question #75
PMI-RMP Question #75: Real Exam Question with Answer & Explanation
The correct answer is B: System or process flowcharts. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?
Options
- APredecessor and successor diagramming
- BSystem or process flowcharts
- CCause and effect diagrams
- DInfluence diagrams
Topics
#Risk identification#Diagramming techniques#Process flowcharts#System analysis
Community Discussion
No community discussion yet for this question.