PMI-RMP · Question #265
PMI-RMP Question #265: Real Exam Question with Answer & Explanation
The correct answer is C: Risks may be listed by priority separately for schedule, cost, and performance. See the full explanation below for the reasoning.
Question
Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his company, on several risks within the project. Tom understands that through qualitative analysis Neil has identified many risks in the project. Tom's concern, however, is that the priority list of these risk events are sorted in "high-risk," "moderate-risk," and "low-risk" as conditions apply within the project. Tom wants to know that is there any other objective on which Neil can make the priority list for project risks. What will be Neil's reply to Tom?
Options
- ARisks may be listed by the additional analysis and response
- BRisk may be listed by the responses in the near-term
- CRisks may be listed by priority separately for schedule, cost, and performance
- DRisks may be listed by categories
Topics
Community Discussion
No community discussion yet for this question.