The correct answer is C: Risk management plan. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?

Options

  • AEnterprise environmental factors
  • BRisk register
  • CRisk management plan
  • DStaffing management plan

Topics

#Risk management plan#Roles and responsibilities#Risk planning