PMIPMI
PMI-RMP · Question #263
PMI-RMP Question #263: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #263. The question stem and answer options stay visible for context.
Risk Monitoring and Reporting
Question
Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen. If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?
Options
- A$35,000
- B$41,700
- C$14,000
- D$6,700
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Contingency Reserve#Expected Monetary Value (EMV)#Risk Budget Management#Quantitative Risk Analysis