You are the project manager for Genpact Inc. You have established quarterly risk management meetings. Which of the following is not a component of a risk management meeting?
The correct answer is D. The availability of the individual. The availability of an individual is NOT a component of a risk management meeting. Risk management meetings focus on project-related risk activities: assessing the overall status of risks (A), reviewing risk responses (B), and assessing risks (C). Whether a specific individual…
Question
You are the project manager for Genpact Inc. You have established quarterly risk management meetings. Which of the following is not a component of a risk management meeting?
Options
- AAssessing the overall status of risks in the project
- BReview of risk responses
- CAssessment or risk
- DThe availability of the individual
How the community answered
(20 responses)- A5% (1)
- D95% (19)
Explanation
The availability of an individual is NOT a component of a risk management meeting. Risk management meetings focus on project-related risk activities: assessing the overall status of risks (A), reviewing risk responses (B), and assessing risks (C). Whether a specific individual is available is a scheduling/resource concern, not a component of the meeting itself.