The correct answer is D: Mitigation. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Which of the following is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold?
Options
- AAvoidance
- BExploit
- CTransference
- DMitigation
Topics
#Risk Response Planning#Threat Response#Mitigation