nerdexam
PMIPMI

PMI-RMP · Question #269

PMI-RMP Question #269: Real Exam Question with Answer & Explanation

The correct answer is B: These risks should be placed on awatchlist for future monitoring.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You are the project manager of the NJJ project. Your enterprise environmental factors require that you establish certain risk management rules regarding low risks within your project. What is the best policy for risks with low probability and low impact in the project management?

Options

  • AThese risks should be accepted.
  • BThese risks should be placed on awatchlist for future monitoring.
  • CThese risks should be identified, but dismissed.
  • DThese risks should be placed in the risk register.

Topics

#Risk response strategies#Low priority risks#Watchlist#Risk monitoring

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions