PMI
PMI-RMP · Question #234
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she an
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #234. The question stem and answer options stay visible for context.
Risk Process Facilitation
Question
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
Options
- AThe events should be entered into qualitative risk analysis.
- BThe events should be determined if they need to be accepted or responded to.
- CThe events should be entered into the risk register.
- DThe events should continue on with quantitative risk analysis.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Identification#Risk Register#Risk Management Process Flow#Quantitative Risk Analysis