PMIPMI
PMI-RMP · Question #234
PMI-RMP Question #234: Real Exam Question with Answer & Explanation
The correct answer is C: The events should be entered into the risk register.. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
Options
- AThe events should be entered into qualitative risk analysis.
- BThe events should be determined if they need to be accepted or responded to.
- CThe events should be entered into the risk register.
- DThe events should continue on with quantitative risk analysis.
Topics
#Risk Identification#Risk Register#Risk Management Process Flow#Quantitative Risk Analysis
Community Discussion
No community discussion yet for this question.