PMI-RMP · Question #313
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?
The correct answer is C. Change requests, cost plan, and project documents. When scope, schedule, and cost begin to increase during Monitor and Control Project Work, the outputs that must be updated or created are change requests, the cost plan, and project documents. Change requests are required to formally initiate any corrective or preventive…
Question
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?
Options
- AProject management plan, project documents, and human resource plan
- BChange requests, project management plan, and project documents
- CChange requests, cost plan, and project documents
- DEnterprise environmental factors, change requests, and project management plan
How the community answered
(24 responses)- A13% (3)
- B17% (4)
- C67% (16)
- D4% (1)
Explanation
When scope, schedule, and cost begin to increase during Monitor and Control Project Work, the outputs that must be updated or created are change requests, the cost plan, and project documents. Change requests are required to formally initiate any corrective or preventive actions. The cost plan must be updated to reflect the new cost reality. Project documents (such as the risk register, issue log, and lessons learned) must also be updated. Option A is incorrect because the human resource plan is not directly affected by these variances. Option B is partially correct but the broader 'project management plan' is less specific than the cost plan given the cost-focused nature of the change. Option D is incorrect because enterprise environmental factors are inputs to processes, not outputs.
Topics