nerdexam
PMIPMI

PMI-RMP · Question #313

PMI-RMP Question #313: Real Exam Question with Answer & Explanation

The correct answer is C: Change requests, cost plan, and project documents. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?

Options

  • AProject management plan, project documents, and human resource plan
  • BChange requests, project management plan, and project documents
  • CChange requests, cost plan, and project documents
  • DEnterprise environmental factors, change requests, and project management plan

Topics

#Monitor Risks#Change Management#Project Baselines#Project Documents

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions