PMIPMI
PMI-RMP · Question #313
PMI-RMP Question #313: Real Exam Question with Answer & Explanation
The correct answer is C: Change requests, cost plan, and project documents. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
During the risk Monitor and Control Project Work process, the scope, schedule, and cost begin to increase. What outputs should be updated and/or created?
Options
- AProject management plan, project documents, and human resource plan
- BChange requests, project management plan, and project documents
- CChange requests, cost plan, and project documents
- DEnterprise environmental factors, change requests, and project management plan
Topics
#Monitor Risks#Change Management#Project Baselines#Project Documents
Community Discussion
No community discussion yet for this question.