PMI-RMP · Question #311
Contingency Reserve Total: US$213,000 Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?
The correct answer is C. US$157,000. The new contingency reserve total is US$157,000. The difference between the original total (US$213,000) and the new total (US$157,000) is US$56,000, which represents the reduction in Risk 4's expected monetary value (EMV) due to the successful mitigation. EMV = Probability ×…
Question
Contingency Reserve Total: US$213,000 Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?
Exhibit
Options
- AUS$92,400
- BUS$145,800
- CUS$157,000
- DUnable to calculate a total due to lack of pertinent information.
How the community answered
(35 responses)- A3% (1)
- B6% (2)
- C83% (29)
- D9% (3)
Explanation
The new contingency reserve total is US$157,000. The difference between the original total (US$213,000) and the new total (US$157,000) is US$56,000, which represents the reduction in Risk 4's expected monetary value (EMV) due to the successful mitigation. EMV = Probability × Impact. Because Risk 4's probability was reduced to 40%, its EMV decreased, and that reduction flows directly into a lower contingency reserve. The specific impact value for Risk 4 (US$140,000) can be back-calculated: original EMV contribution minus new EMV contribution equals US$56,000, consistent with a probability reduction applied to a known impact value. Option D is incorrect because sufficient information is available to perform this calculation.
Topics
Community Discussion
No community discussion yet for this question.
