nerdexam
PMI

PMI-RMP · Question #311

Contingency Reserve Total: US$213,000 Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?

The correct answer is C. US$157,000. The new contingency reserve total is US$157,000. The difference between the original total (US$213,000) and the new total (US$157,000) is US$56,000, which represents the reduction in Risk 4's expected monetary value (EMV) due to the successful mitigation. EMV = Probability ×…

Perform Targeted Risk Analysis

Question

Contingency Reserve Total: US$213,000 Due to a mitigation strategy, Risk 4's probability has been reduced to 40%. What would be the new contingency reserve total?

Exhibit

PMI-RMP question #311 exhibit

Options

  • AUS$92,400
  • BUS$145,800
  • CUS$157,000
  • DUnable to calculate a total due to lack of pertinent information.

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    83% (29)
  • D
    9% (3)

Explanation

The new contingency reserve total is US$157,000. The difference between the original total (US$213,000) and the new total (US$157,000) is US$56,000, which represents the reduction in Risk 4's expected monetary value (EMV) due to the successful mitigation. EMV = Probability × Impact. Because Risk 4's probability was reduced to 40%, its EMV decreased, and that reduction flows directly into a lower contingency reserve. The specific impact value for Risk 4 (US$140,000) can be back-calculated: original EMV contribution minus new EMV contribution equals US$56,000, consistent with a probability reduction applied to a known impact value. Option D is incorrect because sufficient information is available to perform this calculation.

Topics

#Contingency Reserve#Expected Monetary Value (EMV)#Risk Mitigation#Quantitative Risk Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice