nerdexam
PMI

PMI-RMP · Question #310

Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the risk manager do firs

The correct answer is D. Review the change control log.. The first step is to review the change control log to determine whether the unplanned activities were formally approved through the integrated change control process. This provides context before taking any action-the activities may have been legitimately authorized while the ris

Risk Monitoring and Reporting

Question

Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the risk manager do first?

Options

  • AMeet with the project team.
  • BInform management of out-of-scope work.
  • CReview activities for new risks.
  • DReview the change control log.

How the community answered

(67 responses)
  • A
    10% (7)
  • B
    3% (2)
  • C
    6% (4)
  • D
    81% (54)

Explanation

The first step is to review the change control log to determine whether the unplanned activities were formally approved through the integrated change control process. This provides context before taking any action-the activities may have been legitimately authorized while the risk manager was away. Only after establishing whether proper change control was followed should the risk manager meet with the team (A), escalate to management (B), or assess new risks (C). Skipping the change log review could lead to incorrectly assuming a process violation when none occurred, or missing critical risk context tied to approved changes.

Topics

#Change control#Scope management#Risk monitoring#Project governance

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice