nerdexam
PMIPMI

PMI-RMP · Question #280

PMI-RMP Question #280: Real Exam Question with Answer & Explanation

The correct answer is D: Ensuring that each risk identified and deemed critical has a computed expected value. It is not feasible or necessary to quantify every risk. Therefore, a risk audit should never have as an objective to ensure that each project risk has a computed expected value. [Monitoring and PMI®, PMBOK® Guide, 2013, 351

Risk Monitoring and Reporting

Question

Which of the following is NOT an objective of a risk audit?

Options

  • AConfirming that risk management has been practiced throughout the project life cycle
  • BConfirming that the project is well managed and that the risks are being controlled
  • CEvaluating the effectiveness of risk responses in dealing with identified risks
  • DEnsuring that each risk identified and deemed critical has a computed expected value

Explanation

It is not feasible or necessary to quantify every risk. Therefore, a risk audit should never have as an objective to ensure that each project risk has a computed expected value. [Monitoring and PMI®, PMBOK® Guide, 2013, 351

Topics

#Risk Audit#Risk Monitoring#Risk Management Objectives

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions