PMIPMI
PMI-RMP · Question #280
PMI-RMP Question #280: Real Exam Question with Answer & Explanation
The correct answer is D: Ensuring that each risk identified and deemed critical has a computed expected value. It is not feasible or necessary to quantify every risk. Therefore, a risk audit should never have as an objective to ensure that each project risk has a computed expected value. [Monitoring and PMI®, PMBOK® Guide, 2013, 351
Risk Monitoring and Reporting
Question
Which of the following is NOT an objective of a risk audit?
Options
- AConfirming that risk management has been practiced throughout the project life cycle
- BConfirming that the project is well managed and that the risks are being controlled
- CEvaluating the effectiveness of risk responses in dealing with identified risks
- DEnsuring that each risk identified and deemed critical has a computed expected value
Explanation
It is not feasible or necessary to quantify every risk. Therefore, a risk audit should never have as an objective to ensure that each project risk has a computed expected value. [Monitoring and PMI®, PMBOK® Guide, 2013, 351
Topics
#Risk Audit#Risk Monitoring#Risk Management Objectives
Community Discussion
No community discussion yet for this question.