nerdexam
PMIPMI

PMI-RMP · Question #282

PMI-RMP Question #282: Real Exam Question with Answer & Explanation

The correct answer is A: Hold meetings. Meetings are a tool and technique in the control risks process. Risk management should be an agenda item at periodic status meetings. While the amount of time needed for risk management will vary depending on the identified risks, their priority, and the difficulty of the respons

Risk Process Facilitation

Question

One way to make it more likely practice project risk management on projects is to______________

Options

  • AHold meetings
  • BHave the team take an orientation class on risk management early in the project
  • CGive one team member the responsibility for risk management working in conjunction with the PMO
  • DAssign each team member a risk to own, which is documented in the risk register

Explanation

Meetings are a tool and technique in the control risks process. Risk management should be an agenda item at periodic status meetings. While the amount of time needed for risk management will vary depending on the identified risks, their priority, and the difficulty of the response, the more often risk management is practiced, the easier it becomes. Frequent discussions about risk make it more likely that risks and opportunities will be identified. [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 352

Topics

#Risk Management Practice#Team Collaboration#Communication#Risk Process Execution

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions