PMI-RMP · Question #283

PMI-RMP Question #283: Real Exam Question with Answer & Explanation

The correct answer is D: A mechanism to communicate and support project decision making is provided. All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 353-354

Risk Monitoring and Reporting

Question

Work performance information in control risks means that______________

Options

  • ARecommended preventive or corrective action is considered through change requests
  • BOutcomes of risk reassessments and risk audits are documented
  • CTemplates to the risk management plan and the risk register are recommended
  • DA mechanism to communicate and support project decision making is provided

Explanation

All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 353-354

Topics

#Work Performance Information#Control Risks Process#Risk Monitoring#Decision Support