PMIPMI
PMI-RMP · Question #283
PMI-RMP Question #283: Real Exam Question with Answer & Explanation
The correct answer is D: A mechanism to communicate and support project decision making is provided. All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 353-354
Risk Monitoring and Reporting
Question
Work performance information in control risks means that______________
Options
- ARecommended preventive or corrective action is considered through change requests
- BOutcomes of risk reassessments and risk audits are documented
- CTemplates to the risk management plan and the risk register are recommended
- DA mechanism to communicate and support project decision making is provided
Explanation
All of the answers are outputs in the control risks process, however, work performance information specifically provides a mechanism to communicate and support project decision [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 353-354
Topics
#Work Performance Information#Control Risks Process#Risk Monitoring#Decision Support