nerdexam
PMIPMI

PMI-RMP · Question #45

PMI-RMP Question #45: Real Exam Question with Answer & Explanation

The correct answer is B: $233,500. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure: If Risk D happens in this project, how much will be left in the contingency reserve?

Options

  • A$440,000
  • B$233,500
  • C$258,500
  • D$243,500

Topics

#Contingency Reserve#Risk Response Implementation#Risk Budgeting#Quantitative Risk Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions