PMIPMI
PMI-RMP · Question #45
PMI-RMP Question #45: Real Exam Question with Answer & Explanation
The correct answer is B: $233,500. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure: If Risk D happens in this project, how much will be left in the contingency reserve?
Options
- A$440,000
- B$233,500
- C$258,500
- D$243,500
Topics
#Contingency Reserve#Risk Response Implementation#Risk Budgeting#Quantitative Risk Analysis
Community Discussion
No community discussion yet for this question.