nerdexam
PMI

PMI-RMP · Question #45

You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure: If Risk D happens in this projec

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #45. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure:

If Risk D happens in this project, how much will be left in the contingency reserve?

Options

  • A$440,000
  • B$233,500
  • C$258,500
  • D$243,500

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Contingency Reserve#Risk Response Implementation#Risk Budgeting#Quantitative Risk Analysis
Full PMI-RMP Practice