PMI-RMP · Question #46
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including…
The correct answer is B. Risk probability-impact matrix. The risk probability-impact matrix is an INPUT to the Perform Qualitative Risk Analysis process (it comes from the Risk Management Plan), not an output that gets added to the risk register. The risk register updates from qualitative risk analysis include: relative…
Question
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Options
- ATrends in qualitative risk analysis
- BRisk probability-impact matrix
- CWatchlist of low-priority risks
- DRisks grouped by categories
How the community answered
(30 responses)- A3% (1)
- B93% (28)
- C3% (1)
Explanation
The risk probability-impact matrix is an INPUT to the Perform Qualitative Risk Analysis process (it comes from the Risk Management Plan), not an output that gets added to the risk register. The risk register updates from qualitative risk analysis include: relative ranking/priority list of risks, risks grouped by categories, causes of risk, watchlist of low-priority risks, risks requiring further analysis, near-term risks, and trends in qualitative risk analysis results. The probability-impact matrix is a tool/technique used during the process, not something recorded into the risk register afterward.