PMIPMI
PMI-RMP · Question #46
PMI-RMP Question #46: Real Exam Question with Answer & Explanation
The correct answer is B: Risk probability-impact matrix. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Options
- ATrends in qualitative risk analysis
- BRisk probability-impact matrix
- CWatchlist of low-priority risks
- DRisks grouped by categories
Topics
#Qualitative Risk Analysis#Risk Register Updates#Risk Tools and Techniques#Risk Prioritization
Community Discussion
No community discussion yet for this question.