nerdexam
PMI

PMI-RMP · Question #47

Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the techn

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #47. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?

Options

  • ABob is correct. Bob is familiar with the technology and the risk event so his response should be
  • BBob is correct. Not all risk events have to pass the quantitative risk analysis process to
  • CNancy is correct. All risks of significant probability and impact should pass the quantitative risk
  • DNancy is correct. Because Nancy is the project manager she can determine the correct

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management Process#Qualitative Risk Analysis#Quantitative Risk Analysis#Risk Response Planning
Full PMI-RMP Practice