nerdexam
PMIPMI

PMI-RMP · Question #27

PMI-RMP Question #27: Real Exam Question with Answer & Explanation

The correct answer is A: 1.02. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than 0.90. Consider that Pete's project has a budget at completion of $275,000. His project is 65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78 percent complete. What is the cost performance index for this project to determine if the contingency response should happen?

Options

  • A1.02
  • B0.96
  • C0.90
  • D0.89

Topics

#Earned Value Management (EVM)#Cost Performance Index (CPI)#Contingency Response#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions