nerdexam
PMI

PMI-RMP · Question #27

Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than…

The correct answer is A. 1.02. CPI = EV / AC. First, calculate EV: 65% complete × $275,000 BAC = $178,750. AC (actual cost spent) = $175,000. CPI = $178,750 / $175,000 = 1.021 ≈ 1.02. Since 1.02 > 0.90, the contingency response is NOT triggered. The scheduled completion (78%) is a distractor used to…

Risk Monitoring and Reporting

Question

Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than 0.90. Consider that Pete's project has a budget at completion of $275,000. His project is 65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78 percent complete. What is the cost performance index for this project to determine if the contingency response should happen?

Options

  • A1.02
  • B0.96
  • C0.90
  • D0.89

How the community answered

(33 responses)
  • A
    76% (25)
  • B
    15% (5)
  • C
    6% (2)
  • D
    3% (1)

Explanation

CPI = EV / AC. First, calculate EV: 65% complete × $275,000 BAC = $178,750. AC (actual cost spent) = $175,000. CPI = $178,750 / $175,000 = 1.021 ≈ 1.02. Since 1.02 > 0.90, the contingency response is NOT triggered. The scheduled completion (78%) is a distractor used to calculate SV, not CPI. CPI > 1.0 means the project is getting more value per dollar spent than planned (under budget). Option B (0.96) and D (0.89) result from incorrect calculations, and C (0.90) is the threshold itself, not the calculated value.

Topics

#Earned Value Management (EVM)#Cost Performance Index (CPI)#Contingency Response#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice