nerdexam
PMIPMI

PMI-RMP · Question #9

PMI-RMP Question #9: Real Exam Question with Answer & Explanation

The correct answer is C: The amount of detail of repetition that is appropriate depends on how the project progresses relative to its. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment of risks within each project. How much detail and repetition in approach for risks to be reassessed for probability and impact?

Options

  • AEach risk reassessment should go into the same depth as the original risk assessment activity.
  • BThe probability and impact of risk event should determine the level of reassessment throughout the
  • CThe amount of detail of repetition that is appropriate depends on how the project progresses relative to its
  • DThe level of detail and reassessment should reflect the priority of the project.

Topics

#Risk Reassessment#Risk Monitoring and Control#Adaptive Risk Management#Tailoring Risk Management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions