PMI-RMP · Question #8

PMI-RMP Question #8: Real Exam Question with Answer & Explanation

The correct answer is A: Establish the definitions of the levels of probability and impact. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are the project manager for your organization. You are working with your key stakeholders in the qualitative risk analysis process. You understand that there is certain bias towards the risk events in the project that you need to address, manage, and ideally reduce. What solution does the PMBOK recommend to reduce the influence of bias during qualitative risk analysis?

Options

  • AEstablish the definitions of the levels of probability and impact
  • BProvide iterations of risk analysis for true reflection of a risk probability and impact
  • CIsolate the stakeholders by project phases to determine their risk bias
  • DInvolve all stakeholders to vote on the probability and impact of the risk events

Topics

#Qualitative Risk Analysis#Stakeholder Bias#Probability and Impact Scales#Risk Assessment Techniques