nerdexam
PMIPMI

PMI-RMP · Question #1

PMI-RMP Question #1: Real Exam Question with Answer & Explanation

The correct answer is D: -$27,000. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

Examine the figure given below. What will be the expected monetary value of Risk C?

Options

  • A-$113,750
  • B$175,000 if the risk event actually happens
  • C-$175,000
  • D-$27,000

Topics

#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Impact#Risk Probability

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions