PMI-RMP · Question #1
Examine the figure given below. What will be the expected monetary value of Risk C?
The correct answer is D. -$27,000. Expected Monetary Value (EMV) is calculated as: EMV = Probability × Impact. For Risk C (based on the referenced figure), the probability and impact values multiply to yield -$27,000. The negative sign indicates a threat (negative risk event). Choice B is incorrect because EMV…
Question
Examine the figure given below. What will be the expected monetary value of Risk C?
Options
- A-$113,750
- B$175,000 if the risk event actually happens
- C-$175,000
- D-$27,000
How the community answered
(13 responses)- A8% (1)
- B15% (2)
- D77% (10)
Explanation
Expected Monetary Value (EMV) is calculated as: EMV = Probability × Impact. For Risk C (based on the referenced figure), the probability and impact values multiply to yield -$27,000. The negative sign indicates a threat (negative risk event). Choice B is incorrect because EMV is a pre-event calculation of weighted value, not the actual cost if the event occurs. Choice A and C represent the raw impact or miscalculated values. The EMV formula weights the financial impact by the likelihood of occurrence, so the cost of a risk response should not exceed the EMV of the risk.
Topics
Community Discussion
No community discussion yet for this question.