PMIPMI
PMI-RMP · Question #1
PMI-RMP Question #1: Real Exam Question with Answer & Explanation
The correct answer is D: -$27,000. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Examine the figure given below. What will be the expected monetary value of Risk C?
Options
- A-$113,750
- B$175,000 if the risk event actually happens
- C-$175,000
- D-$27,000
Topics
#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Impact#Risk Probability
Community Discussion
No community discussion yet for this question.