The correct answer is B: This is the avoidance risk response.. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?
Options
- AThis is the risk mitigation response.
- BThis is the avoidance risk response.
- CThis is the transference risk response.
- DThis is a scope change and not a risk response.
Topics
#Risk response strategies#Risk avoidance#Threat response#Project management plan changes