PMIPMI
PMI-RMP · Question #24
PMI-RMP Question #24: Real Exam Question with Answer & Explanation
The correct answer is A: Activity cost estimates. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?
Options
- AActivity cost estimates
- BCost management plan
- CActivity duration estimates
- DRisk management plan
Topics
#Identify Risks#Inputs to Identify Risks#Activity Cost Estimates#Risk Identification Techniques
Community Discussion
No community discussion yet for this question.