nerdexam
PMIPMI

PMI-RMP · Question #24

PMI-RMP Question #24: Real Exam Question with Answer & Explanation

The correct answer is A: Activity cost estimates. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

Options

  • AActivity cost estimates
  • BCost management plan
  • CActivity duration estimates
  • DRisk management plan

Topics

#Identify Risks#Inputs to Identify Risks#Activity Cost Estimates#Risk Identification Techniques

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions