Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?
Options
- AResource management plan
- BProject plan
- CProject management plan
- DRisk management plan
Topics
#Risk management plan#Risk planning#Risk procedures#Contingency planning