nerdexam
PMIPMI

PMI-RMP · Question #25

PMI-RMP Question #25: Real Exam Question with Answer & Explanation

The correct answer is D: Risk management plan. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?

Options

  • AResource management plan
  • BProject plan
  • CProject management plan
  • DRisk management plan

Topics

#Risk management plan#Risk planning#Risk procedures#Contingency planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions