The correct answer is B: Perform qualitative analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?

Options

  • ARisk identification
  • BPerform qualitative analysis
  • CPerform quantitative analysis
  • DRisk Breakdown Structure creation

Topics

#Qualitative risk analysis#Risk prioritization#Probability and impact assessment#Risk analysis techniques

Community Discussion

No community discussion yet for this question.